Our Lord is a living god and he answers to all our prayers. We have moved this far all because of the Grace he has given to us through our prayers. He is our provider and our organization is lame with out prayer support so we just want to keep some of our prayer request here so that you all would pray and our dreams will be achieved.
1. Financial Support to Construct the School Building.(Detail is Given)
MAKE MY SCHOOL
(A Project of Darjeeling Himalayan Kids Club)
Budget Plan for the Construction of School Building
Name of the Project : Shalom English School
Location : Chota Hatta,P.O.Bansbotay,Darjeeling.
Distance from Main Town(Darjeeling) : 70km
School Estd. : 2010
Total no of Students : 26 students
Total no of Room at present : 3 Class rooms+ 1 staff room
To Construct Two Class Rooms of 14ft x 11ft Budget plan
Sl No |
Particulars |
Qty |
Amount
(Rs.) |
1 |
Wooden planks/beams |
100qft @ Rs.210/-qft
* |
21,000.00 |
2 |
Stones /Pebbles |
20 piles (1mtx1mt)@Rs600/-pile * |
12,000.00 |
3 |
Cements |
20bags @Rs.530/-bag
* |
10,600.00 |
4 |
Sands |
120 bags @Rs.60/-bag * |
7,200.00 |
5 |
Iron & Rods |
1quintal (8mm) @Rs.6000/-quintal * |
6000.00 |
6 |
Steel Sheet for Roofs and Walls |
8ft (2bundles)& 6ft(2bundles) @Rs.6500/- per bundle * |
25,000.00 |
7 |
Window Glass Panes |
|
5000.00 |
8 |
Desk & Charis |
20pec @Rs.500/-( Including Making Charge) |
10,000.00 |
9 |
Black Board |
2pec @Rs.1000/-(Including Making Charge) |
2000.00 |
10 |
Paints and Colors |
|
2000.00 |
11 |
Miscellaneous Expenses |
|
|
12 |
i) Nails |
10 kg @ Rs.60/- kg |
600.00 |
13 |
ii) Angles |
36pec @Rs.20/-pec |
720.00 |
14 |
iii) binding Wires |
5kg @Rs.55/-kg |
275.00 |
15 |
Labour Charges |
|
|
|
i) Head labour |
Rs.250/- per day x 2months |
15,000.00 |
|
ii) 2 Asst. labour |
Rs.180/- per day x per labour x 2months |
21,600.00 |
|
|
TOTAL |
1,38,995.00 |
(Rupees One Lakh
Thirty Eight Thousand Nine Hundred and Ninety Five) only. Approx
(* INDICATE- INCLUDES CARRYING CHARGES)
Site Plan of the School (SHALOM ENGLISH SCHOOL)
|